Dentistry For Kids
Dentistry for Kids, Monroeville, PA, ground-up construction, 12,000 sq ft. The original contract amounted to $3.3 million, but through CBRE’s early involvement providing full-service project management, the cost was negotiated down to $2.7 million, resulting in a significant saving of $600,000 for the client.
Construction began on April 17, 2019, and concluded on October 15, 2019, a tight 6-month timeline. The project faced challenges, including delays caused by difficulties in securing financing approval and the power company frequently changing the location of power poles and transformers, incurring an additional $64,000 in costs. Nonetheless, coordination with vendors, adherence to schedules, and cooperation with local authorities ensured successful inspections and allowed Dentistry for Kids to open as planned.